Teem meeting on 4-29
Attendees: Everyone on the team
Meeting Place: 132 Woodland
Meeting Time: April 29 at 8AM -9AM
Quick Meeting
Need to finish gestures, the problem is that it detects the gestures but just stops working randomly.
Current week objectives:
Need to finish gestures
Finish PowerPoint
Current week accomplishments:
Updated project plan
Finished keyboard functionality
IST331_Fall14_Team4_Blog
Tuesday, April 29, 2014
Monday, April 21, 2014
Saturday, April 19, 2014
Teem meeting on 4-17
Teem meeting on 4-17
Attendees: Everyone on the team
Meeting Place: 132 Woodland
Meeting Time: April 17at 8AM -9AM
Quick Meeting
We just need to add gesture
5 finger swipe left- it opens keyboard
5 finger swipe left- closes keyboard
when clicked on button on touch wheel, we need to program it to open up the software.
we need to figure out how to drag and drop software to add to the touch wheel
Current week objectives:
Development
Current week accomplishments:
Updated project plan
Attendees: Everyone on the team
Meeting Place: 132 Woodland
Meeting Time: April 17at 8AM -9AM
Quick Meeting
We just need to add gesture
5 finger swipe left- it opens keyboard
5 finger swipe left- closes keyboard
when clicked on button on touch wheel, we need to program it to open up the software.
we need to figure out how to drag and drop software to add to the touch wheel
Current week objectives:
Development
Current week accomplishments:
Updated project plan
Tuesday, April 8, 2014
Teem meeting on 4-08
Teem meeting on 4-8
Attendees: Everyone on the team
Meeting Place: 132 Woodland
Meeting Time: March 19 at 9AM -10AM
Quick Meeting
We have started programming and we are thinking of adding a gesture where double tap on the touch wheel will show the keyboard.
Current week objectives:
Development
Current week accomplishments:
Finished the design for the keyboard and touch wheel
Added all the projects into one
Updated project plan
Attendees: Everyone on the team
Meeting Place: 132 Woodland
Meeting Time: March 19 at 9AM -10AM
Quick Meeting
We have started programming and we are thinking of adding a gesture where double tap on the touch wheel will show the keyboard.
Current week objectives:
Development
Current week accomplishments:
Finished the design for the keyboard and touch wheel
Added all the projects into one
Updated project plan
Sunday, March 23, 2014
Thursday, March 20, 2014
3-19
Teem meeting on 3-19
Attendees: Everyone on the team
Meeting Place: 132 Woodland
Meeting Time: March 19 at 7:00AM -7:30PM
Quick Meeting
John's laptop is not functional properly so Kha will let john borrow his extra laptop . Everyone will have some work designed or programmed by next meeting.
Current week objectives:
Start Development
Current week accomplishments:
Updated Project Plan
Attendees: Everyone on the team
Meeting Place: 132 Woodland
Meeting Time: March 19 at 7:00AM -7:30PM
Quick Meeting
John's laptop is not functional properly so Kha will let john borrow his extra laptop . Everyone will have some work designed or programmed by next meeting.
Current week objectives:
Start Development
Current week accomplishments:
Updated Project Plan
Thursday, March 13, 2014
Teem meeting on 3-13
Teem meeting on 3-13
Attendees: Everyone on the team
Meeting Place: Google hangout
Meeting Time: March 13 at 8PM -8:30PM
Quick Meeting
We need to start developing the app. We split parts of individual's responsibility for this project.
Muhammad & Frankie: Program functionality of the keyboard
Khu & John : Make the design of the keyboard
Vimal & Frankie: Work on the blade and disk prototype.
Current week objectives:
Updated Project Plan
Start Development
Current week accomplishments:
Finished keyboard prototype
Attendees: Everyone on the team
Meeting Place: Google hangout
Meeting Time: March 13 at 8PM -8:30PM
Quick Meeting
We need to start developing the app. We split parts of individual's responsibility for this project.
Muhammad & Frankie: Program functionality of the keyboard
Khu & John : Make the design of the keyboard
Vimal & Frankie: Work on the blade and disk prototype.
Current week objectives:
Updated Project Plan
Start Development
Current week accomplishments:
Finished keyboard prototype
Subscribe to: